Projects/ Programs | Ref. Number (Budget) | Amount Budgeted | Amount Released | Budget Credibility | Project/Program Status | Location | Social Audit Observation | Statutory Audit Findings | EROSION CONTROL AND CHANNELIZATION WORKS AT NRI AGUKWU ANAOCHA SOUTH LGA, ANAMBRA STATE | ERGP20103883 | 50,000,000.00 | | | | | | | |
RE-ACTIVATION OF EXISTING AND INSTALLATION OF NEW AUTOMATED FLOOD EARLY WARNING SYSTEM (FEWS) IN 2 RIVER BASINS OF THE COUNTRY | ERGP20103894 | 8,000,000.00 | | | | | | | |
EROSION CONTROL IN UDEGE TOWN, NASARAWA STATE | ERGP20103921 | 30,000,000.00 | | | | | | | |
OBINAGU ETITI ROAD/EKE-OBINAGU AND NKPOLO GULLY EROSION CONTROL, ENUGWU AGIDI NJIKOKA LGA, ANAMBRA STATE | ERGP20104091 | 50,000,000.00 | | | | | | | |
ESTABLISHMENT OF ACACIA SENEGAL PLANTATION IN THE FRONTLINE STATES TO ARREST LAND DEGRADATION AND MITIGATE THE EFFECTS OF DROUGHT AND CLIMATE CHANGE | ERGP20104204 | 20,000,000.00 | | | | | | | |
ESTABLISHMENT OF WOODLOTS IN TWO (2) GEOPOLITICAL ZONES OF NORTH CENTRAL NORTH WEST | ERGP20104207 | 25,000,000.00 | | | | | | | |
CONSTRUCTION OF SIDE DRAINS AND ROAD IMPROVEMENT OF OGBOROMA-ONICHA ROAD, OHAOZARA LGA, EBONYI STATE | ERGP20104431 | 20,400,001.00 | | | | | | | |
EROSION AND FLOOD CONTROL PROJECT AT LASSA TOWN ASKIRA-UBA LGA, BORNO STATE | ERGP20104470 | 40,000,000.00 | | | | | | | |
IRUOBIELI-IFITE-AMAOBIA ROAD GULLY EROSION CONTROL, ANAMBRA STATE | ERGP20104499 | 50,343,735.00 | | | | | | | |
EROSION AND FLOOD CONTROL IN UNGUWAN FARANSA, GOMBI LGA, ADAMAWA STATE | ERGP20104526 | 36,000,000.00 | | | | | | | |
CULVERTS AND DRAINAGE CONTROL IN WABARA STREET, GWORAMBILI, MARAMA IN HAWUL LOCAL GOVERNMENT AREA, BORNO STATE | ERGP20104669 | 20,000,000.00 | | | | | | | |
EROSION CONTROL WORKS IN ETITINABO, ANAOCHA LGA, ANAMBRA STATE | ERGP20110613 | 20,000,000.00 | | | | | | | |
AFFORESTATION/REFORESTATION PROGRAMME NATIONWIDE | ERGP20110828 | 100,695,000.00 | | | | | | | |
PROVISION OF UNDERGROUND WATER STORAGE SYSTEM IN THE ARID ZONES TO MITIGATE THE EFFECTS OF DROUGHT AND CLIMATE CHANGE. | ERGP20111928 | 33,000,000.00 | | | | | | | |
NATIONAL IMPLEMENTATION OF NIGERIA'S NDC | ERGP20111999 | 20,000,000.00 | | | | | | | |
UNITED NATIONS FRAMEWORK CONVENTION ON CLIMATE CHANGE CONFERENCE OF PARTIES (UNFCCC; COP) ENABLING ACTIVITY | ERGP20112010 | 70,000,000.00 | | | | | | | |
EROSION CONTROL IN ADA-OKERE-UKONI-AMEDOKHIAN OLD ROAD IN EDO STATE (CONTRACT NO. FMENV/EFCZM/CAP2010/S.123: RETENSION PAYMENT) | | 5,841,051.00 | | | | | | | |
DEVELOPMENT AND IMPLEMENTATION OF A STRATEGIC SUSTAINABLE CLIMATE CHANGE AND ENVIRONMENTAL ADVOCACY PROGRAMME PHASE III | ERGP20112032 | 15,000,000.00 | | | | | | | |
DEVELOPMENT OF CLIMATE CHANGE DESK/UNIT IN STATE MINISTRIES OF ENVIRONMENT AND ALL RELEVANT MDAs | ERGP20112039 | 13,800,000.00 | | | | | | | |
CRITICAL SUPPORT AND CAPACITY BUILDING TO STRENGTHEN LINKS WITH CLIMATE CHANGE LINKAGE AND RESEARCH CENTRES | ERGP20112069 | 20,000,000.00 | | | | | | | |
CLIMATE CHANGE MITIGATION/ADAPTATION PROJECT FOR ALTERNATIVE ENERGY PRODUCTION TO POWER BOREHOLE FOR PORTABLE DRINKING WATER IN THREE COMMUNITIES ACROSS THE COUNTRY PHASE III | ERGP20112084 | 20,000,000.00 | | | | | | | |
EROSION CONTROL AND ROAD REHABILITATION WORKS ALONG GARKI-AGUNGWU OGBOO ROAD, UGWUOBA, OJI RIVER LGA, ENUGU STATE | ERGP20125645 | 20,000,000.00 | | | | | | | |
EROSION CONTROL WORKS IN FUTU, MICHIKA ADAMAWA STATE | ERGP20125679 | 20,000,000.00 | | | | | | | |
EZIAMA NTIGHA FLOOD CHANNELIZATION PROJECT, ISIALA NGWA NORTH LGA, ABIA STATE | ERGP20125764 | 10,000,000.00 | | | | | | | |
CONSTRUCTION OF FLOOD CONTROL WORKS AT AMAO FARM, ILORIN WEST LGA, KWARA STATE | ERGP20125787 | 10,000,000.00 | | | | | | | |
CONSTRUCTION OF CULVERTS EROSION CONTROL WORKS IN OKUNDI NEW LAYOUT, OKUNDI BOKI LGA, CROSS RIVER STATE | ERGP20125801 | 15,000,000.00 | | | | | | | |
EROSION CONTROL AT ISANLU-ISIN LGA KWARA STATE | ERGP20125846 | 31,000,000.00 | | | | | | | |
ROAD IMPROVEMENT WORKS AND DRAINAGES IN ELUOBODO AMUZU AMAGU ROAD, IVO LGA | ERGP20138955 | 60,000,000.00 | | | | | | | |
EROSION CONTROL AT UNGUWAN DOSA KADUNA NORTH, KADUNA STATE | ERGP20139038 | 50,000,000.00 | | | | | | | |
CHANNELIZATION AND FLOOD CONTROL IN TUDUNWADA, KADUNASOUTH, KADUNA STATE | ERGP20139042 | 80,000,000.00 | | | | | | | |
EROSION CONTROL AT RIGASA IN IGABI LGA, KADUNA STATE | ERGP20139053 | 60,000,000.00 | | | | | | | |
RIVER JAMTARI FLOODING CONTROL IN MAYO BELWA LGA, ADAMAWA STATE | ERGP20139059 | 50,000,000.00 | | | | | | | |
EROSION CONTROL IN OBOSI, IDEMILI LGA, ANAMBRA STATE | ERGP20139066 | 80,000,000.00 | | | | | | | |
EROSION AND FLOOD CONTROL WORK ON IYI OKWO-OGUBI ROAD AT AGBOHA, ABIA STATE | ERGP20139133 | 10,000,000.00 | | | | | | | |
CHANNELIZATION AND ROAD IMPROVEMENT FOR FLOOD CONTROL ALONG NUT-PEACE MALL ROAD, SABON LUGBE AND AMAC ESTATE PH2, ABUJA | ERGP20139141 | 50,000,000.00 | | | | | | | |
EROSION CONTROL AND ROAD REHABILITATION ALONG EMOT EFA UGATE FARM ROAD, OKURIKE TOWN, BIASE LGA, CROSS RIVER STATE. | ERGP20139148 | 20,000,000.00 | | | | | | | |
EROSION CONTROL AND ROAD IMPROVEMENT AT AGBONDEUDU- OGWUNGODO, AMACHI AFIKPO NORTH LGA, EBONYI STATE | ERGP20139153 | 15,000,000.00 | | | | | | | |
GULLY EROSION CONTROL AT IKAPTANG, ISHIBORR IN OGOJA LGA, CROSS RIVER STATE | ERGP20139223 | 20,000,000.00 | | | | | | | |
INSTALLATION OF SOLAR CARPORTS IN FEDERAL MINISTRY OF ENVIRONMENT OFFICES | ERGP20139743 | 20,000,000.00 | | | | | | | |
CLIMATE CHANGE VULNERABILITY MAPPING | ERGP20139744 | 10,100,000.00 | | | | | | | |
ENHANCING NATIONAL ACCESS TO GLOBAL CLIMATE FINANCE | ERGP20139745 | 20,000,000.00 | | | | | | | |
NATIONAL GREEN BOND IMPLEMENTATION PROGRAMME | ERGP20139748 | 20,000,000.00 | | | | | | | |
STAKEHOLDERS' ENGAGEMENT ON ADAPTIVE MEASURES TO CLIMATE CHANGE | ERGP20139752 | 8,400,000.00 | | | | | | | |
AWARENESS CREATION ON CLIMATE CHANGE PROGRAMME IN THE NORTH-WEST GEOPOLITICAL ZONE | ERGP20139761 | 8,000,000.00 | | | | | | | |
AWARENESS CREATION ON CLIMATE CHANGE PROGRAMME IN THE SOUTH-EAST GEOPOLITICAL ZONE | ERGP20139762 | 8,000,000.00 | | | | | | | |
AWARENESS CREATION ON CLIMATE CHANGE PROGRAMME IN THE NORTH-EAST GEOPOLITICAL ZONE | ERGP20139763 | 8,000,000.00 | | | | | | | |
AWARENESS CREATION ON CLIMATE CHANGE PROGRAMME IN THE SOUTH-SOUTH GEOPOLITICAL ZONE | ERGP20139765 | 8,000,000.00 | | | | | | | |
AWARENESS CREATION ON CLIMATE CHANGE PROGRAMME IN THE SOUTH-WEST GEOPOLITICAL ZONE | ERGP20139768 | 8,000,000.00 | | | | | | | |
AWARENESS CREATION ON CLIMATE CHANGE PROGRAMME IN THE NORTH-CENTRAL GEOPOLITICAL ZONE | ERGP20139770 | 8,000,000.00 | | | | | | | |
MAINSTREAMING CLIMATE CHANGE IN TO NATIONAL DEVELOPMENT PLANNING | ERGP20139774 | 8,000,000.00 | | | | | | | |
CONSTRUCTION OF SOLAR POWERED BOREHOLE FOR CLIMATE CHANGE ADAPTATION IN PANTAMI GOMBE STATE AND THREE OTHER COMMUNITIES | ERGP20143283 | 20,000,000.00 | | | | | | | |
REHABILITATION OF GULLY ERODED SITE AT FURFURI TOWN, BUNGUDU LGA, ZAMFARA STATE | ERGP20149420 | 20,000,000.00 | | | | | | | |
EROSION CONTROL AT AKIRIBOTO COMMUNITY, AYEDAADE LGA, GBONGAN, OSUN STATE | ERGP20149421 | 15,000,000.00 | | | | | | | |
EROSION MENACE AT ANIANTA IN NDIANICHE-UNO, IDEATO NORTH LGA, IMO STATE | ERGP20150107 | 10,000,000.00 | | | | | | | |
OKE-AOFIN FLOOD CONTROL WORKS, ERITI AKOKO NORTH WEST, ONDO STATE | ERGP20150108 | 20,000,000.00 | | | | | | | |
IGASI/ERITI AKOKO AND OMUO EKITI BOUNDARY CULVERT COLLAPSE, EROSION CONTROL AND ROAD IMPROVEMENT PROJECT, IGASI/ERITI AKOKO, ONDO STATE | ERGP20150109 | 20,000,000.00 | | | | | | | |
KAINJI TOWN FLOOD AND EROSION CONTROL WORKS, NIGER STATE | ERGP20150110 | 20,000,000.00 | | | | | | | |
FLOOD CONTROL PROJECT AT DOEMAK, QUANPAN LGA, PLATEAU STATE | ERGP20150111 | 20,000,000.00 | | | | | | | |
EDOZHIGI GULLY EROSION CONTROL WORKS, NIGER STATE | ERGP20150114 | 15,000,000.00 | | | | | | | |
EROSION CONTROL IN SHARE COMMUNITY, IFELODUN LGA, KWARA STATE | ERGP20150116 | 50,000,000.00 | | | | | | | |
CONSTRUCTION OF DRAINS AND CULVERTS TO CONTROL EROSION AND FLOOD PROBLEM BEHIND OLD ARMY BARRACK, SULEJA, NIGER STATE | ERGP20150118 | 20,000,000.00 | | | | | | | |
ANGUWAN MAKARFI/RAILWAY GULLY EROSION AND FLOOD CONTROL KATCHA, NIGER STATE | ERGP20150119 | 5,000,000.00 | | | | | | | |
ANGUWAN YORUBAWA/RAILWAY GULLY EROSION AND FLOOD CONTROL KATCHA, NIGER STATE | ERGP20150120 | 5,000,000.00 | | | | | | | |
EROSION AND FLOOD CONTROL WORKS IN UKE, NASARAWA STATE | ERGP20150121 | 10,000,000.00 | | | | | | | |
FLOOD AND EROSION CONTROL PROJECT AT AMANKALU, ALAYI AND OZUITEM IN BENDE FEDERAL CONSTITUENCY, ABIA STATE | ERGP20150122 | 5,000,000.00 | | | | | | | |
EROSION AND FLOOD CONTROL/ROAD IMPROVEMENT WORKS AT FOUR CORNER OGBUDO UMUOGAZI/UMUDIJI UGWUORIE UKPOR NNEWI SOUTH LGA, ANAMBRA STATE | ERGP20150127 | 5,000,000.00 | | | | | | | |
EROSION AND FLOOD CONTROL/ROAD IMPROVEMENT WORKS AT UGWU ORIE UKPOR UMUOCHI LILU ORSU IHITE UKWA IN NNEWI SOUTH/IHIALA/ORSU LGA's ANAMBRA STATE | ERGP20150128 | 5,000,000.00 | | | | | | | |
EROSION CONTROL WORKS AND ROAD REHABILITATION AT HOUSING ESTATE 33 ONITSHA ANAMBRA STATE - FMENV/PROC/CAP/2018/EFCZM/020/I | ERGP20150129 | 50,000,000.00 | | | | | | | |
CONSTRUCTION OF SIDE DRAINS AND CULVERTS IN KULANI BALANGA LGA, GOMBE STATE | ERGP20150149 | 20,000,000.00 | | | | | | | |
PROVISION AND INSTALLATION OF LOCAL AUTOMATIC WEATHERSTATIONS FOR DROUGHT EARLY WARNING SYSTEM FOR LOCAL DROUGHT | ERGP20151238 | 50,571,051.00 | | | | | | | |
EROSION CONTROL WORKS ALONG UMUANUNU ALAIKE UMUNUMO ROAD IN EHIME MBANO LGA, ABIA STATE | ERGP20151528 | 15,000,000.00 | | | | | | | |
EROSION AND FLOOD CONTROL AT YANYAN OYO ROAD, IWO LGA, OSUN STATE | ERGP20151536 | 17,000,000.00 | | | | | | | |
EROSION CONTROL WORKS IN IPEE, FUFU, OLOKO IGBONLA COMMUNITIES IN OYUN LGA, KWARA STATE | ERGP20151548 | 18,000,000.00 | | | | | | | |
CONTROL OF EROSION SITES AT HOSPITAL ROAD, AMAEKPU IN OHAFIA LGA, ABIA NORTH SENATORIAL DISTRICT, ABIA STATE | ERGP20151555 | 5,000,000.00 | | | | | | | |
FLOOD CONTROL WITH DRAINAGE IN BORIPE COMMUNITY, EGBEDORE LGA, OSOGBO, OSUN STATE | ERGP20151748 | 60,000,000.00 | | | | | | | |
PROVISION OF SOLAR-POWERED STREET LIGHT AT UNGUWAN MISSION COMMUNITY, LASSA ASKIRA UBA LGA, BORNO STATE | ERGP20152156 | 30,000,000.00 | | | | | | | |
PROVISION OF SOLAR POWERED STREET LIGHT AT UNGUWAN ZAHU GONI GORA , CHIKUN LGA, KADUNA STATE | ERGP20152160 | 20,000,000.00 | | | | | | | |
PROVISION OF SOLAR POWERED STREET LIGHT AT UNGUWAN FARANSA, GOMBI LGA, ADAMAWA STATE | ERGP20152161 | 20,000,000.00 | | | | | | | |
RENEWABLE ENERGY PROJECT, SOLAR-POWERED GRINDING MACHINES, SOLAR POWERED ACQUISITION CENTRE (MULTIPURPOSE) AS WELL AS TRAINING FOR YOUTHS AT GWANARA, YASHIKARA, GURE, ILESA, CHIKANDA, GWASORO, KAIAMA COMMUNITY OF KWARA STATE | ERGP20152163 | 20,000,000.00 | | | | | | | |
ESTABLISHMENT OF NATIONAL GREEN HOUSE GASES INVENTORY MANAGEMENT SYSTEM | ERGP20152166 | 15,000,000.00 | | | | | | | |
DEVELOPMENT OF COUNTRY-SPECIFIC EMISSION FACTOR FOR THE ENERGY AND AFOLU SECTORS IN NIGERIA | ERGP20152168 | 10,000,000.00 | | | | | | | |
WEB SITE AND MOBILE APPLICATION DEVELOPMENT FOR CLIMATE CHANGE COMMUNICATION AND STAKEHOLDER ENGAGEMENT | ERGP20152170 | 5,242,103.00 | | | | | | | |
DEVELOPMENT OF IMPLEMENTATION STRATEGY FOR THE NATIONAL ACTION PLAN ON GENDER AND CLIMATE CHANGE | ERGP20152173 | 10,000,000.00 | | | | | | | |
ODOKWE-IRUCHIMA-AMUDA-OMELEGUDE EROSION CONTROL IN NTEJE, OYI LGA, ANAMBRA STATE | ERGP20152250 | 25,000,000.00 | | | | | | | |
EROSION AND FLOOD CONTROL AT USUNGWE UVETE UKEHI LGA, KOGI STATE | ERGP20152627 | 20,000,000.00 | | | | | | | |
CONSTRUCTION OF SOLAR-POWERED BOREHOLE FOR CLIMATE CHANGE ADAPTATION IN IYEKU TOWN ODO-OTIN LGA COMMUNITIES, | ERGP20152669 | 30,000,000.00 | | | | | | | |
CONSTRUCTION OF SOLAR POWERED BOREHOLE FOR CLIMATE CHANGE ADAPTATION IN OKE IPA ATAKUMASA WEST LGA, OSUN STATE | ERGP20152740 | 20,000,000.00 | | | | | | | |
NATIONAL CHEMICAL INVENTORY AND THEIR RISK ASSESSMENT | ERGP20153383 | 6,000,000.00 | | | | | | | |
EROSION CONTROL WORKS AT SALUWA, ORIMOLADE, ONDO WEST LGA, ONDO STATE | ERGP20153385 | 30,000,000.00 | | | | | | | |
IGBP OJA, ITANLA GRA FLOOD AND EROSION CONTROL WORKS, ONDO STATE | ERGP20153386 | 25,000,000.00 | | | | | | | |
ENVIRONMENTAL HEALTH SURVELLANCE | ERGP20153390 | 30,932,949.00 | | | | | | | |
EBA COMMUNITY EROSION CONTROL PROJECT, UDI LGA, ENUGU STATE | ERGP20153692 | 100,000,000.00 | | | | | | | |
EROSION CONTROL PROJECT AT OMI ATAN, FANIBI ROAD, AKURE | ERGP20155211 | 15,000,000.00 | | | | | | | |
FLOOD AND EROSION CONTROL WORKS AT EMEYAL 2 COMMUNITY OGBIA LGA, BAYELSA STATE | ERGP20157192 | 30,000,001.00 | | | | | | | |